Supreme Court, Appellate Division, Second Department, New York.
JACK C. HIRSCH, INC., Appellant,
v.
The TOWN OF NORTH HEMPSTEAD, Respondent.  (Action No. 1)
BARLO EQUIPMENT CORPORATION, Plaintiff,
v.
JACK C. HIRSCH, INC., Appellant.  (Action No. 2)
Nov. 25, 1991.
 Public contractor brought action to recover for work performed on plumbing 
contract and subcontract with town.   The Supreme Court, Nassau County, 
O'Shaughnessy, J., granted town's summary judgment motion.   Appeal was taken.   
The Supreme Court, Appellate Division, held that:  (1) statements made by 
contractor in separate action brought against it by subcontractor were 
admissible in action against town, and (2) contractor's admissions in separate 
action that work was not properly performed supported finding that contractor 
had breached contract.
 Affirmed.
West Headnotes
[1] Evidence  208(2)
157k208(2) Most Cited Cases
Admission by public contractor in pleading in action brought against it by 
subcontractor was admissible against contractor in its action to recover amounts 
owed from town where it could be shown that facts were alleged with contractor's 
knowledge or under his direction;  pleading was verified and allegations were 
not made upon information and belief.
[2] Evidence  265(7)
157k265(7) Most Cited Cases
Admissions made by public contractor in action brought against it by 
subcontractor to effect that work performed did not meet its agreement with town 
established that contractor had breached contract, and, thus, admissions could 
be introduced against contractor in contractor's action to recover amounts owed 
from town.
 **76 Kirschenbaum & Kirschenbaum, P.C., Garden City (Burton Aronson, of 
counsel), for appellant in Action Nos. 1 and 2.
 Diana Centrella Prevete, Town Atty., Manhasset (Betty A. Maier, of counsel), 
for respondent.
 Before KUNZEMAN, J.P., and SULLIVAN, BALLETTA and COPERTINO, JJ.
 MEMORANDUM BY THE COURT.
 In separate actions to recover damages for "work, labor, and services performed 
and materials furnished" pursuant to a plumbing contract and a subcontract, the 
plaintiff in Action No. 1, appeals from an order of the Supreme Court, Nassau 
County (O'Shaughnessy, J.), dated March 2, 1990, which (1) denied its motion to 
consolidate the actions, and (2) granted the cross motion of the defendant in 
Action No. 1 for summary judgment dismissing the complaint in that action.
 ORDERED that the order is affirmed, with costs.
 The appellant Jack C. Hirsch, Inc. (hereinafter Hirsch), a general contractor, 
commenced Action No. 1 against the defendant Town of North Hempstead 
(hereinafter the Town) to recover the sum of $67,455.22 for work, labor, 
materials and services performed in connection with a plumbing contract.   The 
Town, in its answer, interposed the affirmative defense of breach of contract 
and, thereafter, moved for summary judgment dismissing the complaint.   In 
support of its motion, the Town introduced statements made by Hirsch in a 
counterclaim made in a separate action brought against Hirsch by a 
subcontractor.   Those statements admitted that the work performed on the site 
did not conform with the specifications of the contract between Hirsch and the 
Town.   In opposition to the motion, Hirsch submitted an affidavit which also 
admitted that it did not properly perform its agreement with the Town.
 [1][2] Hirsch argues that the statements made by it in a pleading in a separate 
action are not a proper basis for dismissal of its action against the Town.   We 
disagree.   An admission in a pleading in one action is admissible against the 
pleader in another suit, provided that it can be shown that the facts were 
alleged with the pleader's knowledge or under his direction (see, Richardson, 
Evidence §  217 [Prince 10th ed];  Fisch, Evidence §  804 [2d ed 1977];  Cook v. 
Barr, 44 N.Y. 156).   Furthermore, such an admission is "open to * * * 
explanation" and is "not conclusive" (see, Walsh v. NYC & HRRR Co., 204 N.Y. 58, 
66, 97 N.E. 408;  Talbot v. Laubheim, 188 N.Y. 421, 81 N.E. 163).   Here, it is 
clear that the facts alleged in the counterclaim were made with Hirsch's 
knowledge since the pleading was verified and the allegations were not made upon 
information and belief.   Furthermore, we find that **77 the affidavit submitted 
in opposition to the summary judgment motion was sufficient, with other proof, 
to establish that Hirsch breached its contract with the Town.   Accordingly, 
since there are no material *685 and triable issues of fact, summary judgment 
was properly granted.
 We find the parties' remaining contentions to be without merit.
577 N.Y.S.2d 75, 177 A.D.2d 683
END OF DOCUMENT
Supreme Court, Appellate Division, Second Department, New York.
JACK C. HIRSCH, INC., Appellant,v.The TOWN OF NORTH HEMPSTEAD, Respondent.  (Action No. 1)BARLO EQUIPMENT CORPORATION, Plaintiff,v.JACK C. HIRSCH, INC., Appellant.  (Action No. 2)

Nov. 25, 1991.

 Public contractor brought action to recover for work performed on plumbing contract and subcontract with town.   The Supreme Court, Nassau County, O'Shaughnessy, J., granted town's summary judgment motion.   Appeal was taken.   The Supreme Court, Appellate Division, held that:  (1) statements made by contractor in separate action brought against it by subcontractor were admissible in action against town, and (2) contractor's admissions in separate action that work was not properly performed supported finding that contractor had breached contract.
 Affirmed.

West Headnotes
[1] Evidence  208(2)157k208(2) Most Cited Cases
Admission by public contractor in pleading in action brought against it by subcontractor was admissible against contractor in its action to recover amounts owed from town where it could be shown that facts were alleged with contractor's knowledge or under his direction;  pleading was verified and allegations were not made upon information and belief.
[2] Evidence  265(7)157k265(7) Most Cited Cases
Admissions made by public contractor in action brought against it by subcontractor to effect that work performed did not meet its agreement with town established that contractor had breached contract, and, thus, admissions could be introduced against contractor in contractor's action to recover amounts owed from town. **76 Kirschenbaum & Kirschenbaum, P.C., Garden City (Burton Aronson, of counsel), for appellant in Action Nos. 1 and 2.
 Diana Centrella Prevete, Town Atty., Manhasset (Betty A. Maier, of counsel), for respondent.

 Before KUNZEMAN, J.P., and SULLIVAN, BALLETTA and COPERTINO, JJ.


 MEMORANDUM BY THE COURT.
 In separate actions to recover damages for "work, labor, and services performed and materials furnished" pursuant to a plumbing contract and a subcontract, the plaintiff in Action No. 1, appeals from an order of the Supreme Court, Nassau County (O'Shaughnessy, J.), dated March 2, 1990, which (1) denied its motion to consolidate the actions, and (2) granted the cross motion of the defendant in Action No. 1 for summary judgment dismissing the complaint in that action.
 ORDERED that the order is affirmed, with costs.
 The appellant Jack C. Hirsch, Inc. (hereinafter Hirsch), a general contractor, commenced Action No. 1 against the defendant Town of North Hempstead (hereinafter the Town) to recover the sum of $67,455.22 for work, labor, materials and services performed in connection with a plumbing contract.   The Town, in its answer, interposed the affirmative defense of breach of contract and, thereafter, moved for summary judgment dismissing the complaint.   In support of its motion, the Town introduced statements made by Hirsch in a counterclaim made in a separate action brought against Hirsch by a subcontractor.   Those statements admitted that the work performed on the site did not conform with the specifications of the contract between Hirsch and the Town.   In opposition to the motion, Hirsch submitted an affidavit which also admitted that it did not properly perform its agreement with the Town.
 [1][2] Hirsch argues that the statements made by it in a pleading in a separate action are not a proper basis for dismissal of its action against the Town.   We disagree.   An admission in a pleading in one action is admissible against the pleader in another suit, provided that it can be shown that the facts were alleged with the pleader's knowledge or under his direction (see, Richardson, Evidence §  217 [Prince 10th ed];  Fisch, Evidence §  804 [2d ed 1977];  Cook v. Barr, 44 N.Y. 156).   Furthermore, such an admission is "open to * * * explanation" and is "not conclusive" (see, Walsh v. NYC & HRRR Co., 204 N.Y. 58, 66, 97 N.E. 408;  Talbot v. Laubheim, 188 N.Y. 421, 81 N.E. 163).   Here, it is clear that the facts alleged in the counterclaim were made with Hirsch's knowledge since the pleading was verified and the allegations were not made upon information and belief.   Furthermore, we find that **77 the affidavit submitted in opposition to the summary judgment motion was sufficient, with other proof, to establish that Hirsch breached its contract with the Town.   Accordingly, since there are no material *685 and triable issues of fact, summary judgment was properly granted.
 We find the parties' remaining contentions to be without merit.
577 N.Y.S.2d 75, 177 A.D.2d 683
END OF DOCUMENT