Supreme Court, Appellate Division, Second Department, New York.
J. CASTRONOVO, INC., Respondent,
v.
HILLSIDE DEVELOPMENT CORP., et al., Appellants,
Baker Roofing, Inc., et al., Defendants.
April 9, 1990.
Supreme Court, Westchester County, Palella, J., confirmed an arbitrator's award
in favor of contractor and resettled judgment against principal and surety in
action to foreclose a mechanic's lien, and appeal was taken. The Supreme
Court, Appellate Division, held that: (1) trial court erred in holding that
surety was obligated by terms of its bond to pay arbitration award, which was
made in a proceeding against surety's principal to foreclose a mechanic's lien
in which surety did not participate, and (2) trial court erred in granting
summary judgment against surety in context of an action to foreclose a
mechanic's lien in which surety had not yet appeared; furthermore, since surety
was not a party to arbitration agreement and did not actively participate in the
arbitration, judgment against principal was improperly resettled to include
surety in context of contractor's application to confirm arbitration award.
Order in accordance with opinion.
West Headnotes
[1] Mechanics' Liens 227
257k227 Most Cited Cases
Trial court erred in holding that surety on bond for discharge of lien was
obligated by terms of its bond to pay arbitration award, which was made in a
proceeding against surety's principal to foreclose mechanic's lien, a proceeding
in which surety did not participate.
[2] Mechanics' Liens 227
257k227 Most Cited Cases
Surety on a bond given to discharge a mechanic's lien is not liable unless lien
is proved to have been valid, and surety is free to litigate validity of lien
whenever lienor seeks to enforce it.
[3] Mechanics' Liens 227
257k227 Most Cited Cases
A valid mechanic's lien must be judicially established before a surety may be
made to pay pursuant to his bond.
[4] Judgment 243
228k243 Most Cited Cases
Trial court erred in granting summary judgment against surety in context of an
action to foreclose a mechanic's lien in which surety had not yet appeared;
furthermore, since surety was not a party to arbitration agreement and did not
actively participate in the arbitration, judgment against principal was
improperly resettled to include surety in context of contractor's application to
confirm arbitration award.
[5] Judgment 186
228k186 Most Cited Cases
Summary judgment may not properly be granted in favor of the plaintiff an
against a defendant before issue has been joined and before defendant has been
given an opportunity to assert defenses. McKinney's CPLR 3211(a), par. 4, (b,
c), 3212(a).
**482 Paul H. Martinez, White Plains, for appellants.
Kirschenbaum & Kirschenbaum, P.C., Garden City (Burton Aronson, of counsel),
for respondent.
Before THOMPSON, J.P., and BRACKEN, BROWN and KUNZEMAN, JJ.
MEMORANDUM BY THE COURT.
In an action to foreclose a mechanic's lien, in which the plaintiff moved to
confirm an arbitration award dated September 6, 1988, (1) the defendant Hillside
Development Corp. appeals from a judgment of the Supreme Court, Westchester
County (Palella, J.), entered March 17, 1989, which, upon confirmation of an
arbitrator's award dated September 6, 1988, is in favor of the plaintiff and
against it in the principal sum of $80,967.75; and (2) the defendants Hillside
Development Corp. and Aetna Casualty & Surety Company appeal, as limited by
their brief, from so much of an order and resettled judgment (one paper) of the
same court, entered August 15, 1989, as, upon confirmation of the arbitration
award, dated September 6, 1988, granted that branch of the plaintiff's motion
which was to resettle the judgment entered March 17, 1989, to provide for entry
of judgment against the defendant Aetna Casualty & Surety Company, and is in
favor of the plaintiff and against them in the principal sum of $80,967.75.
ORDERED that the appeal from the judgment entered March 17, 1989, is dismissed
as that judgment was superseded by the order and resettled judgment (one paper),
made upon the plaintiff's motion for resettlement; and it is further,
ORDERED that the order and resettled judgment (one paper), entered August 15,
1989, is modified, on the law and as a matter of discretion, (1) by deleting the
provision thereof which granted that branch of the plaintiff's motion which was
to resettle the judgment entered March 17, 1989, to provide for entry of
judgment against the defendant Aetna Casualty & Surety Company, and by
substituting therefor a provision granting that branch of the plaintiff's motion
which was for the alternative relief of severing the action against the
defendant Aetna Casualty & Surety Company, and (2) by deleting the provision
thereof which is in favor of the plaintiff and against the defendant Aetna
Casualty & Surety Company in the principal sum of $80,967.75; as so modified,
the order and *764 resettled judgment (one paper) is affirmed insofar as
appealed from; and it is further,
ORDERED that the action against the defendant Aetna Casualty & Surety Company
is severed and its time to serve an **483 answer to the amended complaint is
extended until 30 days after service upon it of a copy of this decision and
order, with notice of entry; and it is further,
ORDERED that the defendant Aetna Casualty & Surety Company is awarded one bill
of costs payable by the plaintiff.
In 1985, the plaintiff contractor filed a mechanic's lien with respect to
certain property located in Greenberg, New York, and allegedly owned by
defendant Hillside Development Corp. (hereinafter Hillside). In its amended
notice of mechanic's lien, the plaintiff claimed that it was owed $216,584 for
certain labor which it had performed in connection with a construction project
at that location. The plaintiff subsequently commenced the instant action to
foreclose on the mechanic's lien.
In July 1985, the court, upon the application of Hillside, fixed $220,000 as
the amount of the undertaking needed in order to discharge the lien. A bond in
this amount was subsequently issued by the defendant Aetna Casualty & Surety
Company (hereinafter Aetna) and, by order dated August 22, 1985, the lien was
discharged. The plaintiff later served an amended complaint, dated September
17, 1985, naming Aetna as a party-defendant, and demanding, inter alia, a
judgment in the sum of $216,584 against both Hillside and Aetna. It is not
clear when or how this amended complaint was served. Aetna has not yet answered
this amended complaint.
In October 1985, Hillside moved to compel the plaintiff to arbitrate its claim
and for a stay of the foreclosure action. By order dated December 6, 1985, the
court granted Hillside's application, referred the matter to arbitration, and
stayed all proceedings in the foreclosure action "pending the outcome of
arbitration". On September 6, 1988, an arbitrator made an award in favor of
the plaintiff and against Hillside, which was confirmed by the court by order
dated February 22, 1989. The confirmed arbitration award was subsequently
incorporated in a judgment entered March 17, 1989, in favor of the plaintiff and
against Hillside in the principal sum of $80,967.75.
On March 1, 1989, the plaintiff made a motion, inter alia, for "resettlement"
of the order dated February 22, 1989, "so as to provide for entry of judgment
against" Aetna, in effect, *765 making the arbitration award binding against
Aetna as well as Hillside. In support of this motion, the plaintiff alleged
that Aetna had had the opportunity to participate in the arbitration, and that
Aetna's attorneys had been served with notice of the motion to confirm the
arbitration award.
Hillside opposed the plaintiff's motion and cross-moved to vacate the stay of
the foreclosure action. In support of this cross motion, the attorneys
whorepresented Hillside stated that neither Hillside nor Aetna had served an
answer to the amended complaint in the foreclosure action because they had been
prohibited from doing so by the stay contained in the order dated December 6,
1985.
On April 21, 1989, Aetna made a cross motion to quash a certain subpoena and to
stay enforcement of the judgment entered March 17, 1989. Aetna's attorney
stated that, on or about March 21, 1989, the plaintiff had purported to commence
an entirely new action in Supreme Court, Nassau County, to enforce the March
17th judgment against Aetna. (Aetna has apparently moved to dismiss that action
pursuant to CPLR 3211[a][4]; however, this motion is not part of the present
record.) Aetna's attorney also argued that the Nassau County action
represented an attempt by the plaintiff to circumvent the requirement that it
demonstrate the validity of its lien prior to seeking enforcement of the terms
of Aetna's bond.
The Supreme Court, in an order and resettled judgment (one paper) entered
August 15, 1989, granted the plaintiff's motion for resettlement and, upon
resettlement, entered judgment in the principal sum of $80,967.75 against both
Hillside and Aetna. The court denied Hillside's and Aetna's separate cross
motions, and this appeal followed.
[1][2][3] The court erred in holding that Aetna was obligated by the terms of
its bond to pay the arbitration award, which **484 was made in a proceeding (in
which Aetna did not participate) against Aetna's principal. A surety on a bond
given to discharge a mechanic's lien is not liable unless the lien is proved to
have been valid, and the surety is free to litigate the validity of the lien
whenever the lienor seeks to enforce it. In other words, a valid lien must be
judicially established before a surety may be made to pay pursuant to its bond
(see, Matter of Brescia Constr. Co. v. Walart Constr. Co., 264 N.Y. 260, 190
N.E. 484; Sexauer & Lemke v. Burke & Sons Co., 228 N.Y. 341, 127 N.E. 329;
Berger Mfg. Co. v. City of New York, 206 N.Y. 24, 99 N.E. 153; Milliken Bros.
Inc. v. City of New York, 201 N.Y. 65, 94 N.E. 196; Matter of Cooper v.
Emmanuele, 25 A.D.2d 809, 270 N.Y.S.2d 99; *766A.L. Plumbing & Heating Co. v.
Kesdeit Realty, 15 A.D.2d 546, 223 N.Y.S.2d 6; Simonelli v. Guidone & Son,
Inc., 201 App.Div. 44, 194 N.Y.S. 104; Bernardo v. Steelco, 115 Misc.2d 1020,
1022-23, 455 N.Y.S.2d 177; 76 N.Y.Jur.2d, Mechanic's Liens, § 124).
[4][5] The court also erred in summarily granting judgment against Aetna in the
context of an action to foreclose a mechanic's lien in which Aetna had not yet
appeared. Summary judgment may not properly be granted in favor of a plaintiff
and against a defendant before issue has been joined and before the defendant
has been given an opportunity to assert defenses (see, CPLR 3212 [a]; City of
Rochester v. Chiarella, 65 N.Y.2d 92, 101-102, 490 N.Y.S.2d 174, 479 N.E.2d
810;cf., CPLR 3211[a], [b], [c]; Four Seasons Hotels v. Vinnik, 127 A.D.2d 310,
515 N.Y.S.2d 1; see also, Republic Nat. Bank of N.Y. v. Luis Winston, Inc., 107
A.D.2d 581, 582, 483 N.Y.S.2d 311 [premature motion for summary judgment made by
defendant, against plaintiff, may be treated as one pursuant to CPLR 3211(a) ]
). Also, unlike the defendant Hillside, Aetna was not a party to the
arbitration agreement, and did not actively participate in the arbitration.
Thus, the judgment against Hillside was improperly resettled to include Aetna in
the context of the plaintiff's application to confirm the arbitration award
(CPLR 7510).
The plaintiff argues that Aetna defaulted in appearing in the foreclosure
action and that its appeal must be dismissed. According to this argument, the
court-ordered stay, which prevented Aetna and Hillside from serving an answer to
the plaintiff's amended complaint expired on October 20, 1988, when the
arbitrator finally denied a motion to modify his earlier award. Thus,
according to the plaintiff, Aetna defaulted when it failed to serve its answer
within 20 days thereafter (see, CPLR 3012[a] ).
The plaintiff's argument regarding Aetna's alleged default was not made in the
Supreme Court and need not be entertained for this reason alone. Moreover, the
present record does not furnish an adequate basis upon which to review this
argument, because it cannot be conclusively determined (1) whether Aetna was
ever properly served with process at all, or (2) assuming that Aetna was
properly served, whether the plaintiff took the appropriate steps toward the
entry of a default judgment in a timely manner (see, CPLR 3215[c] ).
In conclusion, we find that the Supreme Court properly confirmed the
arbitrator's award insofar as it was against the defendant Hillside, and
properly granted a money judgment against Hillside based upon that award.
However, since Aetna is entitled to litigate the validity of the lien, the
judgment *767 insofar as it is against Aetna, must be vacated. We modify the
order and resettled judgment (one paper) accordingly. Because the appellants
do not raise any issue concerning the denial of Aetna's cross motion insofar as
it was to quash certain subpoenas, the order and resettled judgment (one paper),
as so modified, is affirmed insofar as appealed from. Aetna must serve its
answer to the amended complaint (if it has not already done so), at which time
the parties will be free to litigate the procedural issues mentioned above,
including whether Aetna was in technical default, whether any such technical
default should be excused (CPLR 5015), and whether the plaintiff acted promptly
to remedy any such default (CPLR 3215[c] ).
553 N.Y.S.2d 481, 160 A.D.2d 763
END OF DOCUMENT
Supreme Court, Appellate Division, Second Department, New York.J. CASTRONOVO, INC., Respondent,v.HILLSIDE DEVELOPMENT CORP., et al., Appellants,Baker Roofing, Inc., et al., Defendants.
April 9, 1990.
Supreme Court, Westchester County, Palella, J., confirmed an arbitrator's award in favor of contractor and resettled judgment against principal and surety in action to foreclose a mechanic's lien, and appeal was taken. The Supreme Court, Appellate Division, held that: (1) trial court erred in holding that surety was obligated by terms of its bond to pay arbitration award, which was made in a proceeding against surety's principal to foreclose a mechanic's lien in which surety did not participate, and (2) trial court erred in granting summary judgment against surety in context of an action to foreclose a mechanic's lien in which surety had not yet appeared; furthermore, since surety was not a party to arbitration agreement and did not actively participate in the arbitration, judgment against principal was improperly resettled to include surety in context of contractor's application to confirm arbitration award.
Order in accordance with opinion.
West Headnotes
[1] Mechanics' Liens 227257k227 Most Cited Cases
Trial court erred in holding that surety on bond for discharge of lien was obligated by terms of its bond to pay arbitration award, which was made in a proceeding against surety's principal to foreclose mechanic's lien, a proceeding in which surety did not participate.
[2] Mechanics' Liens 227257k227 Most Cited Cases
Surety on a bond given to discharge a mechanic's lien is not liable unless lien is proved to have been valid, and surety is free to litigate validity of lien whenever lienor seeks to enforce it.
[3] Mechanics' Liens 227257k227 Most Cited Cases
A valid mechanic's lien must be judicially established before a surety may be made to pay pursuant to his bond.
[4] Judgment 243228k243 Most Cited Cases
Trial court erred in granting summary judgment against surety in context of an action to foreclose a mechanic's lien in which surety had not yet appeared; furthermore, since surety was not a party to arbitration agreement and did not actively participate in the arbitration, judgment against principal was improperly resettled to include surety in context of contractor's application to confirm arbitration award.
[5] Judgment 186228k186 Most Cited Cases
Summary judgment may not properly be granted in favor of the plaintiff an against a defendant before issue has been joined and before defendant has been given an opportunity to assert defenses. McKinney's CPLR 3211(a), par. 4, (b, c), 3212(a). **482 Paul H. Martinez, White Plains, for appellants.
Kirschenbaum & Kirschenbaum, P.C., Garden City (Burton Aronson, of counsel), for respondent.
Before THOMPSON, J.P., and BRACKEN, BROWN and KUNZEMAN, JJ.
MEMORANDUM BY THE COURT.
In an action to foreclose a mechanic's lien, in which the plaintiff moved to confirm an arbitration award dated September 6, 1988, (1) the defendant Hillside Development Corp. appeals from a judgment of the Supreme Court, Westchester County (Palella, J.), entered March 17, 1989, which, upon confirmation of an arbitrator's award dated September 6, 1988, is in favor of the plaintiff and against it in the principal sum of $80,967.75; and (2) the defendants Hillside Development Corp. and Aetna Casualty & Surety Company appeal, as limited by their brief, from so much of an order and resettled judgment (one paper) of the same court, entered August 15, 1989, as, upon confirmation of the arbitration award, dated September 6, 1988, granted that branch of the plaintiff's motion which was to resettle the judgment entered March 17, 1989, to provide for entry of judgment against the defendant Aetna Casualty & Surety Company, and is in favor of the plaintiff and against them in the principal sum of $80,967.75.
ORDERED that the appeal from the judgment entered March 17, 1989, is dismissed as that judgment was superseded by the order and resettled judgment (one paper), made upon the plaintiff's motion for resettlement; and it is further,
ORDERED that the order and resettled judgment (one paper), entered August 15, 1989, is modified, on the law and as a matter of discretion, (1) by deleting the provision thereof which granted that branch of the plaintiff's motion which was to resettle the judgment entered March 17, 1989, to provide for entry of judgment against the defendant Aetna Casualty & Surety Company, and by substituting therefor a provision granting that branch of the plaintiff's motion which was for the alternative relief of severing the action against the defendant Aetna Casualty & Surety Company, and (2) by deleting the provision thereof which is in favor of the plaintiff and against the defendant Aetna Casualty & Surety Company in the principal sum of $80,967.75; as so modified, the order and *764 resettled judgment (one paper) is affirmed insofar as appealed from; and it is further,
ORDERED that the action against the defendant Aetna Casualty & Surety Company is severed and its time to serve an **483 answer to the amended complaint is extended until 30 days after service upon it of a copy of this decision and order, with notice of entry; and it is further,
ORDERED that the defendant Aetna Casualty & Surety Company is awarded one bill of costs payable by the plaintiff.
In 1985, the plaintiff contractor filed a mechanic's lien with respect to certain property located in Greenberg, New York, and allegedly owned by defendant Hillside Development Corp. (hereinafter Hillside). In its amended notice of mechanic's lien, the plaintiff claimed that it was owed $216,584 for certain labor which it had performed in connection with a construction project at that location. The plaintiff subsequently commenced the instant action to foreclose on the mechanic's lien.
In July 1985, the court, upon the application of Hillside, fixed $220,000 as the amount of the undertaking needed in order to discharge the lien. A bond in this amount was subsequently issued by the defendant Aetna Casualty & Surety Company (hereinafter Aetna) and, by order dated August 22, 1985, the lien was discharged. The plaintiff later served an amended complaint, dated September 17, 1985, naming Aetna as a party-defendant, and demanding, inter alia, a judgment in the sum of $216,584 against both Hillside and Aetna. It is not clear when or how this amended complaint was served. Aetna has not yet answered this amended complaint.
In October 1985, Hillside moved to compel the plaintiff to arbitrate its claim and for a stay of the foreclosure action. By order dated December 6, 1985, the court granted Hillside's application, referred the matter to arbitration, and stayed all proceedings in the foreclosure action "pending the outcome of arbitration". On September 6, 1988, an arbitrator made an award in favor of the plaintiff and against Hillside, which was confirmed by the court by order dated February 22, 1989. The confirmed arbitration award was subsequently incorporated in a judgment entered March 17, 1989, in favor of the plaintiff and against Hillside in the principal sum of $80,967.75.
On March 1, 1989, the plaintiff made a motion, inter alia, for "resettlement" of the order dated February 22, 1989, "so as to provide for entry of judgment against" Aetna, in effect, *765 making the arbitration award binding against Aetna as well as Hillside. In support of this motion, the plaintiff alleged that Aetna had had the opportunity to participate in the arbitration, and that Aetna's attorneys had been served with notice of the motion to confirm the arbitration award.
Hillside opposed the plaintiff's motion and cross-moved to vacate the stay of the foreclosure action. In support of this cross motion, the attorneys whorepresented Hillside stated that neither Hillside nor Aetna had served an answer to the amended complaint in the foreclosure action because they had been prohibited from doing so by the stay contained in the order dated December 6, 1985.
On April 21, 1989, Aetna made a cross motion to quash a certain subpoena and to stay enforcement of the judgment entered March 17, 1989. Aetna's attorney stated that, on or about March 21, 1989, the plaintiff had purported to commence an entirely new action in Supreme Court, Nassau County, to enforce the March 17th judgment against Aetna. (Aetna has apparently moved to dismiss that action pursuant to CPLR 3211[a][4]; however, this motion is not part of the present record.) Aetna's attorney also argued that the Nassau County action represented an attempt by the plaintiff to circumvent the requirement that it demonstrate the validity of its lien prior to seeking enforcement of the terms of Aetna's bond.
The Supreme Court, in an order and resettled judgment (one paper) entered August 15, 1989, granted the plaintiff's motion for resettlement and, upon resettlement, entered judgment in the principal sum of $80,967.75 against both Hillside and Aetna. The court denied Hillside's and Aetna's separate cross motions, and this appeal followed.
[1][2][3] The court erred in holding that Aetna was obligated by the terms of its bond to pay the arbitration award, which **484 was made in a proceeding (in which Aetna did not participate) against Aetna's principal. A surety on a bond given to discharge a mechanic's lien is not liable unless the lien is proved to have been valid, and the surety is free to litigate the validity of the lien whenever the lienor seeks to enforce it. In other words, a valid lien must be judicially established before a surety may be made to pay pursuant to its bond (see, Matter of Brescia Constr. Co. v. Walart Constr. Co., 264 N.Y. 260, 190 N.E. 484; Sexauer & Lemke v. Burke & Sons Co., 228 N.Y. 341, 127 N.E. 329; Berger Mfg. Co. v. City of New York, 206 N.Y. 24, 99 N.E. 153; Milliken Bros. Inc. v. City of New York, 201 N.Y. 65, 94 N.E. 196; Matter of Cooper v. Emmanuele, 25 A.D.2d 809, 270 N.Y.S.2d 99; *766A.L. Plumbing & Heating Co. v. Kesdeit Realty, 15 A.D.2d 546, 223 N.Y.S.2d 6; Simonelli v. Guidone & Son, Inc., 201 App.Div. 44, 194 N.Y.S. 104; Bernardo v. Steelco, 115 Misc.2d 1020, 1022-23, 455 N.Y.S.2d 177; 76 N.Y.Jur.2d, Mechanic's Liens, § 124).
[4][5] The court also erred in summarily granting judgment against Aetna in the context of an action to foreclose a mechanic's lien in which Aetna had not yet appeared. Summary judgment may not properly be granted in favor of a plaintiff and against a defendant before issue has been joined and before the defendant has been given an opportunity to assert defenses (see, CPLR 3212 [a]; City of Rochester v. Chiarella, 65 N.Y.2d 92, 101-102, 490 N.Y.S.2d 174, 479 N.E.2d 810;cf., CPLR 3211[a], [b], [c]; Four Seasons Hotels v. Vinnik, 127 A.D.2d 310, 515 N.Y.S.2d 1; see also, Republic Nat. Bank of N.Y. v. Luis Winston, Inc., 107 A.D.2d 581, 582, 483 N.Y.S.2d 311 [premature motion for summary judgment made by defendant, against plaintiff, may be treated as one pursuant to CPLR 3211(a) ] ). Also, unlike the defendant Hillside, Aetna was not a party to the arbitration agreement, and did not actively participate in the arbitration. Thus, the judgment against Hillside was improperly resettled to include Aetna in the context of the plaintiff's application to confirm the arbitration award (CPLR 7510).
The plaintiff argues that Aetna defaulted in appearing in the foreclosure action and that its appeal must be dismissed. According to this argument, the court-ordered stay, which prevented Aetna and Hillside from serving an answer to the plaintiff's amended complaint expired on October 20, 1988, when the arbitrator finally denied a motion to modify his earlier award. Thus, according to the plaintiff, Aetna defaulted when it failed to serve its answer within 20 days thereafter (see, CPLR 3012[a] ).
The plaintiff's argument regarding Aetna's alleged default was not made in the Supreme Court and need not be entertained for this reason alone. Moreover, the present record does not furnish an adequate basis upon which to review this argument, because it cannot be conclusively determined (1) whether Aetna was ever properly served with process at all, or (2) assuming that Aetna was properly served, whether the plaintiff took the appropriate steps toward the entry of a default judgment in a timely manner (see, CPLR 3215[c] ).
In conclusion, we find that the Supreme Court properly confirmed the arbitrator's award insofar as it was against the defendant Hillside, and properly granted a money judgment against Hillside based upon that award. However, since Aetna is entitled to litigate the validity of the lien, the judgment *767 insofar as it is against Aetna, must be vacated. We modify the order and resettled judgment (one paper) accordingly. Because the appellants do not raise any issue concerning the denial of Aetna's cross motion insofar as it was to quash certain subpoenas, the order and resettled judgment (one paper), as so modified, is affirmed insofar as appealed from. Aetna must serve its answer to the amended complaint (if it has not already done so), at which time the parties will be free to litigate the procedural issues mentioned above, including whether Aetna was in technical default, whether any such technical default should be excused (CPLR 5015), and whether the plaintiff acted promptly to remedy any such default (CPLR 3215[c] ).
553 N.Y.S.2d 481, 160 A.D.2d 763
END OF DOCUMENT