Court of Appeals of New York.
805 THIRD AVE. CO., Appellant,
v.
M.W. REALTY ASSOCIATES, Respondent, et al., Defendant.
March 31, 1983.
Suit was brought seeking rescission of modified contract for sale of air
rights, and related relief, on theory of economic duress. The Supreme Court at
Special Term, New York County, Andrew R. Tyler, J., granted buyer's motion for
preliminary injunction against seller, though not against issuer of letter of
credit, and denied seller's cross motion to dismiss, and seller appealed. The
Supreme Court, Appellate Division, First Judicial Department, 87 A.D.2d 544, 448
N.Y.S.2d 15, modified order by vacating preliminary injunction and granting
cross motion to dismiss complaint, and affirmed, and buyer appealed. The Court
of Appeals, Simons, J., held that: (1) date on which construction of foundation
started was the "Sales Closing Date" on which, under contract, buyer was
required to perform preconditions for transfer of air rights under terms of
contract, which was annexed to the complaint, and (2) since buyer failed to do
so, seller did not have duty to perform, and buyer failed to state cause of
action for economic duress.
Appellate Division affirmed.
West Headnotes
[1] Contracts 95(3)
95k95(3) Most Cited Cases
Theory of economic duress permits complaining party to void a contract and
recover damages when it establishes that it was compelled to agree to the
contract terms because of a wrongful threat by the other party which precluded
the exercise of its free will.
[2] Contracts 237(2)
95k237(2) Most Cited Cases
Existence of economic duress is demonstrated by proof that one party to contract
has threatened the breach of the agreement by withholding performance unless the
other party agrees to some further demand.
[3] Pleading 307
302k307 Most Cited Cases
Where plaintiff annexed to complaint the contract at issue, it made the contract
a part of its pleading for all purposes. McKinney's CPLR 3014.
[4] Contracts 176(1)
95k176(1) Most Cited Cases
Interpretation of contract is a legal matter for the court.
[5] Pleading 307
302k307 Most Cited Cases
Provisions of contract annexed to plaintiff's complaint established the rights
of the parties and prevailed over conclusory allegations of the complaint.
McKinney's CPLR 3014 comment.
[6] Vendor and Purchaser 75
400k75 Most Cited Cases
Under contract for sale of air rights whereby buyer was to deliver to seller on
"Sales Closing Date" cash down payment, promissory note, letter of credit and
architectural drawings and "Sales Closing Date" was defined as earlier of date
on which buyer received authorization to begin or on which it did begin
excavation or any other construction activity, date on which construction of
foundation started was the "Sales Closing Date" even though buyer had not yet
received final approval for 31-story office building for which it was acquiring
the air rights, where the construction undertaken was for the erection of such a
building.
[7] Vendor and Purchaser 343(4)
400k343(4) Most Cited Cases
Where buyer did not perform preconditions for transfer of air rights, seller had
no obligation to perform under the contract, and thus complaint charging seller
with economic duress in subsequently compelling execution of contract
modification by threatening not to perform, and seeking rescission of modified
contract, failed to plead an actionable wrong, and buyer could not claim that
its nonperformance was excused or was defensive matter.
[8] Contracts 95(1)
95k95(1) Most Cited Cases
Party cannot be guilty of economic duress for refusing to do that which it is
not legally required to do.
*448 ***779 **446 Richard E. Hershenson and Samuel Kirschenbaum, New York
City, for appellant.
*449 Jay A. Kranis, Thomas J. Malmud and Barbara L. Levine, New York City, for
respondent.
OPINION OF THE COURT
SIMONS, Judge.
In September, 1979 plaintiff, 805 Third Avenue Co., and defendant, M.W. Realty
Associates, [FN*] two limited partnerships, entered into a contract for the sale
by defendant of a portion of its air rights to plaintiff. In July, 1980 the
parties modified the contract and in May, 1981 plaintiff instituted this action
charging defendant with economic duress in compelling execution of the 1980
modification. It seeks to rescind the modified contract, to recover
compensatory and punitive damages, and to obtain other related relief. After
the action was commenced, plaintiff obtained preliminary injunctive relief from
Special Term which maintained the status quo prior to trial. At the same time
defendant moved to dismiss the complaint for failure to state a cause of action
(CPLR 3211, subd. [a], par. 7). Special Term denied defendant's cross motion.
On appeal, the Appellate Division modified Special Term's order by vacating the
preliminary injunction and granting the cross motion to dismiss (87 A.D.2d 544).
Plaintiff appeals from that order. It contends that its complaint states a
cause of action, that in effect the Appellate Division has held that it must
plead performance of conditions precedent in the September contract contrary to
CPLR 3015 and that the Appellate Division has improperly dismissed the complaint
*450 and granted judgment against it without prior notice (see CPLR 3015;
Rovello v. Orofino Realty Co., 40 N.Y.2d 633, 389 N.Y.S.2d 314, 357 N.E.2d 970).
Defendant contends that the complaint must be judged by considering the terms of
the 1979 contract annexed to it and that when that is done plaintiff's complaint
fails as a matter of law. We agree with defendant.
FN* Defendant Citibank, N.A., is named as a party only because it issued a
letter of credit for the benefit of defendant M.W. Realty Associates. It has
not participated in this appeal.
Briefly, it appears from the complaint that plaintiff is the ground lessee of
the entire blockfront on Third Avenue between 49th and 50th Streets in New York
City except for a two-story building on the northeast corner of 49th Street and
Third Avenue which is owned by defendant. Plaintiff desired to construct an
office building on the site and in order to increase to 31 stories the lawful
floor area permitted under the city's zoning laws, it agreed to ***780 **447
purchase the air rights necessary for the additional stories from defendant for
$1,900,000. The details of the purchase were set forth in a contract dated
September 18, 1979. By its terms plaintiff agreed to deliver in escrow a cash
down payment and a promissory note for the balance of the purchase price which
was to be paid over eight years. In turn defendant agreed to deliver in escrow
a declaration of zoning lot restrictions and a single lot and easement agreement
which would complete the transfer of the air rights. The escrow deposits were
to be exchanged on the "Sales Closing Date" set forth in the contract or earlier
at plaintiff's election. After the deliveries to the escrow agents were made,
and relying on the agreement, plaintiff obtained from the city a permit
authorizing it to commence construction of the building foundation only. It
thereafter commenced excavation and construction and let contracts for erection
of the superstructure. Plaintiff then alleges in its complaint that in May,
1980 it demanded that defendant deliver the documents "as required" by the
contract of September 18, 1979; that defendant refused to do so unless
plaintiff agreed to a modification of the September contract on terms more
favorable to defendant; that defendant's refusal was "unconscionable" and
"oppressive" and was done "maliciously" to apply economic duress to plaintiff
because defendant knew that pursuant to the terms of the ground lease any delay
in construction would cause serious and irreparable injury to plaintiff and its
general partners;*451 that compelled by such wrongful acts of defendant and the
economic duress resulting from its wrongful refusal to deliver the documents,
plaintiff executed the modified contract of 1980 to its damage and defendant's
benefit.
[1][2] The theory on which plaintiff seeks recovery permits a complaining party
to void a contract and recover damages when it establishes that it was compelled
to agree to the contract terms because of a wrongful threat by the other party
which precluded the exercise of its free will (Muller Constr. Co. v. New York
Tel. Co., 40 N.Y.2d 955, 956, 390 N.Y.S.2d 817, 359 N.E.2d 328; Austin
Instrument v. Loral Corp., 29 N.Y.2d 124, 130, 324 N.Y.S.2d 22, 272 N.E.2d 533;
Oleet v. Pennsylvania Exch. Bank, 285 App.Div. 411, 137 N.Y.S.2d 779). The
existence of economic duress is demonstrated by proof that one party to a
contract has threatened to breach the agreement by withholding performance
unless the other party agrees to some further demand (Austin Instrument v. Loral
Corp., supra ). Thus, if all we had before us was plaintiff's complaint we
would reverse and deny defendant's motion to dismiss, for accepting the
allegations of the complaint as true, as we must, it alleges a cause of action
upon which plaintiff may recover.
[3][4][5] But that is not all there is before us. Plaintiff has annexed to
its complaint the contract of September 18, 1979 and by doing so it has made the
contract a part of its pleading for all purposes (CPLR 3014; see, also, Wernham
v. Moore, 77 A.D.2d 262, 432 N.Y.S.2d 711). Interpretation of the contract is a
legal matter for the court (West, Weir & Bartel v. Carter Paint Co., 25 N.Y.2d
535, 540, 307 N.Y.S.2d 449, 255 N.E.2d 709; Bethlehem Steel Co. v. Turner
Constr. Co., 2 N.Y.2d 456, 459, 161 N.Y.S.2d 90, 141 N.E.2d 590), and its
provisions establish the rights of the parties and prevail over conclusory
allegations of the complaint (see Miglietta v. Kennecott Copper Corp., 25 A.D.2d
57, 266 N.Y.S.2d 936; Metcalf v. Metcalf, 274 App.Div. 744, 87 N.Y.S.2d 122;
Siegel, Practice Commentaries, McKinney's Cons.Laws of N.Y., Book 7B, CPLR
C3014:9, p. 11; 3 Weinstein-Korn-Miller, N.Y.Civ.Prac., par. 3014.14). Thus,
we must determine defendant's obligation from the contract and if it does not
appear from the pleading as a whole that defendant has wrongfully withheld its
promised performance, the complaint must be dismissed.
Under the terms of the contract of September, 1979 defendant's declaration and
lot agreement were to be delivered *452 to plaintiff on the "Sales Closing
Date". Plaintiff was entitled to the document, however, only if plaintiff
secured delivery to defendant of (a) the cash down payment and promissory ***781
**448 note held in escrow, plus interest, (b) a letter of credit securing
payment of the balance of the purchase price and (c) the architectural drawings
filed with the authorities as proof that the final floor area did not exceed the
area defendant agreed to convey.
Plaintiff does not contend, nor has it pleaded, that it did any of these things
although the contract expressly provides that defendant's delivery of the
declaration and lot agreement is conditioned on plaintiff doing so. Rather, it
contends that the "Sales Closing Date", the time set for its performance in the
contract, had not occurred, that its failure to perform was defensive matter to
be pleaded by defendant and that its performance was excused because of
defendant's refusal to perform.
[6][7] The contract defined the "Sales Closing Date" as "the date of issuance *
* * by the Department of Buildings" of "a Building Permit for the Proposed
Building." Date of issuance, insofar as pertinent here, was defined as the
earlier of the date on which plaintiff received authorization to begin or on
which it actually did begin "excavation or any other construction activity
(exclusive of demolition) for the Proposed Building" (emphasis added).
Concededly, construction of the foundation started on December 4, 1979.
Plaintiff pleads that it had started in its complaint. The dispute between the
parties is whether the foundation work was the start of construction of the
"Proposed Building" within the terms of the contract. Plaintiff contends that it
was not because on December 4, 1979 it had not received final approval for the
31-story office building and therefore the only office building it could legally
erect under the zoning ordinances could not exceed six stories. Obviously,
plaintiff had no intention of building a six- story building, however; the
construction undertaken was for erection of a 31- story building. Lease
arrangements had been negotiated with prospective tenants to occupy such a
building and construction contracts had been let to build it. As a matter of
law, December 4, 1979 was the "Sales Closing Date", the date that plaintiff
began "excavation or*453 any other construction activity * * * for the Proposed
Building", and that was the date plaintiff was required to perform the
preconditions for transfer of the air rights. Since it did not, it has not
pleaded an actionable wrong by defendant and it cannot claim its nonperformance
is excused or is defensive matter.
[8] In short, the contract does not establish that defendant had an absolute
duty to perform, as plaintiff claims. Since plaintiff was not entitled to
performance, plaintiff has failed to state a cause of action for economic duress
for a party cannot be guilty of economic duress for refusing to do that which it
is not legally required to do. Defendant's cross motion should be granted,
therefore, because unlike those cases in which plaintiff's pleading is
sufficient on its face, though his right to recover may be doubtful (see Rich v.
Lefkovits, 56 N.Y.2d 276, 281, 452 N.Y.S.2d 1, 437 N.E.2d 260), this action is
controlled by the contract annexed to the complaint. There is no dispute about
the facts, only a dispute of law concerning the interpretation of that
instrument. Having resolved that dispute in defendant's favor, we must affirm
(see O'Hara v. Del Bello, 47 N.Y.2d 363, 368, 418 N.Y.S.2d 334, 391 N.E.2d 1311;
see Guggenheimer v. Ginzburg, 43 N.Y.2d 268, 275, 401 N.Y.S.2d 182, 372 N.E.2d
17; supra; Muller Constr. Co. v. New York Tel. Co., 40 N.Y.2d 955, 390 N.Y.S.2d
817, 359 N.E.2d 328, supra ).
Accordingly, the order of the Appellate Division, 87 A.D.2d 544, 448 N.Y.S.2d
15, should be affirmed.
COOKE, C.J., and JASEN, JONES, WACHTLER, FUCHSBERG and MEYER, JJ., concur.
Order affirmed, with costs.
461 N.Y.S.2d 778, 58 N.Y.2d 447, 448 N.E.2d 445
END OF DOCUMENT
Court of Appeals of New York.805 THIRD AVE. CO., Appellant,v.M.W. REALTY ASSOCIATES, Respondent, et al., Defendant.
March 31, 1983.
Suit was brought seeking rescission of modified contract for sale of air rights, and related relief, on theory of economic duress. The Supreme Court at Special Term, New York County, Andrew R. Tyler, J., granted buyer's motion for preliminary injunction against seller, though not against issuer of letter of credit, and denied seller's cross motion to dismiss, and seller appealed. The Supreme Court, Appellate Division, First Judicial Department, 87 A.D.2d 544, 448 N.Y.S.2d 15, modified order by vacating preliminary injunction and granting cross motion to dismiss complaint, and affirmed, and buyer appealed. The Court of Appeals, Simons, J., held that: (1) date on which construction of foundation started was the "Sales Closing Date" on which, under contract, buyer was required to perform preconditions for transfer of air rights under terms of contract, which was annexed to the complaint, and (2) since buyer failed to do so, seller did not have duty to perform, and buyer failed to state cause of action for economic duress.
Appellate Division affirmed.
West Headnotes
[1] Contracts 95(3)95k95(3) Most Cited Cases
Theory of economic duress permits complaining party to void a contract and recover damages when it establishes that it was compelled to agree to the contract terms because of a wrongful threat by the other party which precluded the exercise of its free will.
[2] Contracts 237(2)95k237(2) Most Cited Cases
Existence of economic duress is demonstrated by proof that one party to contract has threatened the breach of the agreement by withholding performance unless the other party agrees to some further demand.
[3] Pleading 307302k307 Most Cited Cases
Where plaintiff annexed to complaint the contract at issue, it made the contract a part of its pleading for all purposes. McKinney's CPLR 3014.
[4] Contracts 176(1)95k176(1) Most Cited Cases
Interpretation of contract is a legal matter for the court.
[5] Pleading 307302k307 Most Cited Cases
Provisions of contract annexed to plaintiff's complaint established the rights of the parties and prevailed over conclusory allegations of the complaint. McKinney's CPLR 3014 comment.
[6] Vendor and Purchaser 75400k75 Most Cited Cases
Under contract for sale of air rights whereby buyer was to deliver to seller on "Sales Closing Date" cash down payment, promissory note, letter of credit and architectural drawings and "Sales Closing Date" was defined as earlier of date on which buyer received authorization to begin or on which it did begin excavation or any other construction activity, date on which construction of foundation started was the "Sales Closing Date" even though buyer had not yet received final approval for 31-story office building for which it was acquiring the air rights, where the construction undertaken was for the erection of such a building.
[7] Vendor and Purchaser 343(4)400k343(4) Most Cited Cases
Where buyer did not perform preconditions for transfer of air rights, seller had no obligation to perform under the contract, and thus complaint charging seller with economic duress in subsequently compelling execution of contract modification by threatening not to perform, and seeking rescission of modified contract, failed to plead an actionable wrong, and buyer could not claim that its nonperformance was excused or was defensive matter.
[8] Contracts 95(1)95k95(1) Most Cited Cases
Party cannot be guilty of economic duress for refusing to do that which it is not legally required to do. *448 ***779 **446 Richard E. Hershenson and Samuel Kirschenbaum, New York City, for appellant.
*449 Jay A. Kranis, Thomas J. Malmud and Barbara L. Levine, New York City, for respondent.
OPINION OF THE COURT
SIMONS, Judge.
In September, 1979 plaintiff, 805 Third Avenue Co., and defendant, M.W. Realty Associates, [FN*] two limited partnerships, entered into a contract for the sale by defendant of a portion of its air rights to plaintiff. In July, 1980 the parties modified the contract and in May, 1981 plaintiff instituted this action charging defendant with economic duress in compelling execution of the 1980 modification. It seeks to rescind the modified contract, to recover compensatory and punitive damages, and to obtain other related relief. After the action was commenced, plaintiff obtained preliminary injunctive relief from Special Term which maintained the status quo prior to trial. At the same time defendant moved to dismiss the complaint for failure to state a cause of action (CPLR 3211, subd. [a], par. 7). Special Term denied defendant's cross motion. On appeal, the Appellate Division modified Special Term's order by vacating the preliminary injunction and granting the cross motion to dismiss (87 A.D.2d 544). Plaintiff appeals from that order. It contends that its complaint states a cause of action, that in effect the Appellate Division has held that it must plead performance of conditions precedent in the September contract contrary to CPLR 3015 and that the Appellate Division has improperly dismissed the complaint *450 and granted judgment against it without prior notice (see CPLR 3015; Rovello v. Orofino Realty Co., 40 N.Y.2d 633, 389 N.Y.S.2d 314, 357 N.E.2d 970). Defendant contends that the complaint must be judged by considering the terms of the 1979 contract annexed to it and that when that is done plaintiff's complaint fails as a matter of law. We agree with defendant.
FN* Defendant Citibank, N.A., is named as a party only because it issued a letter of credit for the benefit of defendant M.W. Realty Associates. It has not participated in this appeal.
Briefly, it appears from the complaint that plaintiff is the ground lessee of the entire blockfront on Third Avenue between 49th and 50th Streets in New York City except for a two-story building on the northeast corner of 49th Street and Third Avenue which is owned by defendant. Plaintiff desired to construct an office building on the site and in order to increase to 31 stories the lawful floor area permitted under the city's zoning laws, it agreed to ***780 **447 purchase the air rights necessary for the additional stories from defendant for $1,900,000. The details of the purchase were set forth in a contract dated September 18, 1979. By its terms plaintiff agreed to deliver in escrow a cash down payment and a promissory note for the balance of the purchase price which was to be paid over eight years. In turn defendant agreed to deliver in escrow a declaration of zoning lot restrictions and a single lot and easement agreement which would complete the transfer of the air rights. The escrow deposits were to be exchanged on the "Sales Closing Date" set forth in the contract or earlier at plaintiff's election. After the deliveries to the escrow agents were made, and relying on the agreement, plaintiff obtained from the city a permit authorizing it to commence construction of the building foundation only. It thereafter commenced excavation and construction and let contracts for erection of the superstructure. Plaintiff then alleges in its complaint that in May, 1980 it demanded that defendant deliver the documents "as required" by the contract of September 18, 1979; that defendant refused to do so unless plaintiff agreed to a modification of the September contract on terms more favorable to defendant; that defendant's refusal was "unconscionable" and "oppressive" and was done "maliciously" to apply economic duress to plaintiff because defendant knew that pursuant to the terms of the ground lease any delay in construction would cause serious and irreparable injury to plaintiff and its general partners;*451 that compelled by such wrongful acts of defendant and the economic duress resulting from its wrongful refusal to deliver the documents, plaintiff executed the modified contract of 1980 to its damage and defendant's benefit.
[1][2] The theory on which plaintiff seeks recovery permits a complaining party to void a contract and recover damages when it establishes that it was compelled to agree to the contract terms because of a wrongful threat by the other party which precluded the exercise of its free will (Muller Constr. Co. v. New York Tel. Co., 40 N.Y.2d 955, 956, 390 N.Y.S.2d 817, 359 N.E.2d 328; Austin Instrument v. Loral Corp., 29 N.Y.2d 124, 130, 324 N.Y.S.2d 22, 272 N.E.2d 533; Oleet v. Pennsylvania Exch. Bank, 285 App.Div. 411, 137 N.Y.S.2d 779). The existence of economic duress is demonstrated by proof that one party to a contract has threatened to breach the agreement by withholding performance unless the other party agrees to some further demand (Austin Instrument v. Loral Corp., supra ). Thus, if all we had before us was plaintiff's complaint we would reverse and deny defendant's motion to dismiss, for accepting the allegations of the complaint as true, as we must, it alleges a cause of action upon which plaintiff may recover.
[3][4][5] But that is not all there is before us. Plaintiff has annexed to its complaint the contract of September 18, 1979 and by doing so it has made the contract a part of its pleading for all purposes (CPLR 3014; see, also, Wernham v. Moore, 77 A.D.2d 262, 432 N.Y.S.2d 711). Interpretation of the contract is a legal matter for the court (West, Weir & Bartel v. Carter Paint Co., 25 N.Y.2d 535, 540, 307 N.Y.S.2d 449, 255 N.E.2d 709; Bethlehem Steel Co. v. Turner Constr. Co., 2 N.Y.2d 456, 459, 161 N.Y.S.2d 90, 141 N.E.2d 590), and its provisions establish the rights of the parties and prevail over conclusory allegations of the complaint (see Miglietta v. Kennecott Copper Corp., 25 A.D.2d 57, 266 N.Y.S.2d 936; Metcalf v. Metcalf, 274 App.Div. 744, 87 N.Y.S.2d 122; Siegel, Practice Commentaries, McKinney's Cons.Laws of N.Y., Book 7B, CPLR C3014:9, p. 11; 3 Weinstein-Korn-Miller, N.Y.Civ.Prac., par. 3014.14). Thus, we must determine defendant's obligation from the contract and if it does not appear from the pleading as a whole that defendant has wrongfully withheld its promised performance, the complaint must be dismissed.
Under the terms of the contract of September, 1979 defendant's declaration and lot agreement were to be delivered *452 to plaintiff on the "Sales Closing Date". Plaintiff was entitled to the document, however, only if plaintiff secured delivery to defendant of (a) the cash down payment and promissory ***781 **448 note held in escrow, plus interest, (b) a letter of credit securing payment of the balance of the purchase price and (c) the architectural drawings filed with the authorities as proof that the final floor area did not exceed the area defendant agreed to convey.
Plaintiff does not contend, nor has it pleaded, that it did any of these things although the contract expressly provides that defendant's delivery of the declaration and lot agreement is conditioned on plaintiff doing so. Rather, it contends that the "Sales Closing Date", the time set for its performance in the contract, had not occurred, that its failure to perform was defensive matter to be pleaded by defendant and that its performance was excused because of defendant's refusal to perform.
[6][7] The contract defined the "Sales Closing Date" as "the date of issuance * * * by the Department of Buildings" of "a Building Permit for the Proposed Building." Date of issuance, insofar as pertinent here, was defined as the earlier of the date on which plaintiff received authorization to begin or on which it actually did begin "excavation or any other construction activity (exclusive of demolition) for the Proposed Building" (emphasis added). Concededly, construction of the foundation started on December 4, 1979. Plaintiff pleads that it had started in its complaint. The dispute between the parties is whether the foundation work was the start of construction of the "Proposed Building" within the terms of the contract. Plaintiff contends that it was not because on December 4, 1979 it had not received final approval for the 31-story office building and therefore the only office building it could legally erect under the zoning ordinances could not exceed six stories. Obviously, plaintiff had no intention of building a six- story building, however; the construction undertaken was for erection of a 31- story building. Lease arrangements had been negotiated with prospective tenants to occupy such a building and construction contracts had been let to build it. As a matter of law, December 4, 1979 was the "Sales Closing Date", the date that plaintiff began "excavation or*453 any other construction activity * * * for the Proposed Building", and that was the date plaintiff was required to perform the preconditions for transfer of the air rights. Since it did not, it has not pleaded an actionable wrong by defendant and it cannot claim its nonperformance is excused or is defensive matter.
[8] In short, the contract does not establish that defendant had an absolute duty to perform, as plaintiff claims. Since plaintiff was not entitled to performance, plaintiff has failed to state a cause of action for economic duress for a party cannot be guilty of economic duress for refusing to do that which it is not legally required to do. Defendant's cross motion should be granted, therefore, because unlike those cases in which plaintiff's pleading is sufficient on its face, though his right to recover may be doubtful (see Rich v. Lefkovits, 56 N.Y.2d 276, 281, 452 N.Y.S.2d 1, 437 N.E.2d 260), this action is controlled by the contract annexed to the complaint. There is no dispute about the facts, only a dispute of law concerning the interpretation of that instrument. Having resolved that dispute in defendant's favor, we must affirm (see O'Hara v. Del Bello, 47 N.Y.2d 363, 368, 418 N.Y.S.2d 334, 391 N.E.2d 1311; see Guggenheimer v. Ginzburg, 43 N.Y.2d 268, 275, 401 N.Y.S.2d 182, 372 N.E.2d 17; supra; Muller Constr. Co. v. New York Tel. Co., 40 N.Y.2d 955, 390 N.Y.S.2d 817, 359 N.E.2d 328, supra ).
Accordingly, the order of the Appellate Division, 87 A.D.2d 544, 448 N.Y.S.2d 15, should be affirmed.
COOKE, C.J., and JASEN, JONES, WACHTLER, FUCHSBERG and MEYER, JJ., concur.
Order affirmed, with costs.
461 N.Y.S.2d 778, 58 N.Y.2d 447, 448 N.E.2d 445
END OF DOCUMENT