Daniel B. NICCOLI, Plaintiff-Appellee, v. DENVER BURGLAR ALARM, INC., a Colorado Corporation, Defendant-Appellant
No. 71-341
Court of Appeals of Colorado, Division One
490 P.2d 304; 1971 Colo. App. LEXIS 1044
November 2, 1971
NOTICE: [**1]
Not Selected for Official Publication
CASE SUMMARY
PROCEDURAL POSTURE: Appellant alarm company sought review of the decision of the trial court (Colorado) that entered judgment against it in suit by appellee property owner who sued the alarm company in tort and contract for damages sustained as a result of a burglary.
OVERVIEW: The alarm company contracted with the property owner to install an alarm system and the contract included the provision that should the alarm be triggered the alarm company would dispatch an agent to the property. The property was burglarized but the alarm company failed to dispatch an agent. The property owner filed suit in tort and contract for damages. The lower court dismissed the tort negligence action but found in the property owner's favor on the contract theory. The court affirmed because the alarm company failed to abide by its agreement. The court also found the judgment amount was proper because it was based on the liquidated damage clause in the contract and was not a penalty.
OUTCOME: The court affirmed the decision of the lower court that entered judgment against the alarm company in suit by the property owner who sued the alarm company in tort and contract for damages sustained as a result of a burglary.
HN2
COUNSEL: No appearance for Plaintiff-Appellee.
Roger E. Stevens, Boulder, for Defendant-Appellant.
JUDGES: Coyte, Judge. Silverstein, C. J., and Pierce, J., concur.
OPINIONBY: COYTE
OPINION: [*305] This is an appeal by the Denver Burglar Alarm Company, defendant below, from a judgment for fifty dollars entered in favor of the plaintiff. Plaintiff has chosen not to make an appearance on appeal.
The facts are these. The defendant contracted to install a burglar alarm system in plaintiff's place of business. The contract provided that in case the alarm went off, the defendant would immediately dispatch one of its agents to plaintiff's business. The contract further provided:
"* * * * the Contractor's liability hereunder shall be limited to a fixed sum of fifty dollars or ten percent of the annual service charge whichever is greater, as liquidated damages, and not as a penalty, and this liability shall be exclusive."
Plaintiff's business was burglarized and the defendant failed to dispatch an agent to plaintiff's place of business as agreed upon. Plaintiff thereupon sued the defendant both in tort and in contract for damages sustained [**2] as a result of the burglary. The defendant generally denied all liability and counterclaimed for $180, this being the amount plaintiff owed on the contract.
Trial was to the court, which found in defendant's favor on its counterclaim. Insofar as plaintiff was concerned, the court dismissed the cause of action based on negligence, but found in plaintiff's favor on the contract theory since the defendant did fail to abide by its agreement to send an agent to plaintiff's business when the alarm went off. Governed by the liquidated damages provision of the contract, the court found in plaintiff's favor in the amount of fifty dollars.
The error asserted by the defendant is that it is not liable for any damages sustained by plaintiff, either in tort or in contract, because it is not responsible for the losses suffered by the plaintiff.
[*306] We disagree with this assertion. There can be no doubt but that the defendant breached its contract with the plaintiff when it failed to dispatch an agent to plaintiff's place of business. HN1Ordinarily, when a breach of contract occurs the party causing the breach is liable to the other party concerned for the damages resulting from the breach. [**3] In certain cases where the contract itself sets forth an amount as damages to be recovered in case of a breach, this figure is used in allowing recovery, unless the figure is deemed to be a penalty.
HN2The essential elements necessary for valid and enforceable liquidated damages clause are: (1) the anticipated damages in case of a breach must be difficult to ascertain, (2) the parties must mutually intend to liquidate them in advance, and (3) the amount stated as liquidated damages must be reasonable and proportionate to the presumed injury occurring as a result of any breach. Perino v. Jarvis, 135 Colo. 393, 312 P.2d 108. The intent of the parties is the determining factor in whether or not a sum named in the contract shall be regarded as liquidated damages rather than a penalty. Such an intent must be found from the wording used, as well as from the attendant facts and circumstances surrounding the particular case. Moore v. Kline, 26 Colo.App. 334, 143 P. 262.
The facts here leave little doubt but that this contractual provision was intended to operate as a liquidated damages clause rather than a penalty. The facts meet the requirements set forth in Perino, supra, since is [**4] was extremely difficult to anticipate precisely any potential damages occurring as a result of defendant's breach.
Insofar as the intention of the parties is concerned, we take note of the fact that this was a printed contract supplied by the defendant, and we therefore consider any provisions in the contract strictly in favor of the plaintiff and against the defendant who prepared the instrument. Christmas v. Cooley, 158 Colo. 297, 406 P.2d 333. Inasmuch as the defendant prepared the instrument setting fifty dollars for damages in case it failed to perform and then specifically stated that this figure was not to be construed as a penalty but rather as liquidated damages, we hold the defendant must abide by the terms it chose to use and that this figure is a liquidated damages clause and not a penalty.
Judgment affirmed.
SILVERSTEIN, C. J., and PIERCE, J., concu